Nightly I-95 lane closings coming to Jupiter, public meeting Tuesday

Nightly

Night I-95 lane closures from Indiantown Road north to Bridge Road in Martin County will occur Sunday through Thursday nights from 9 p.m. until 6 a.m. (File photo)

Night lane closures on I-95 from Indiantown Road in Jupiter north to Bridge Road in Martin County are the subject of a public meeting Tuesday, May 2 from 4 p.m. – 6 p.m. at the FDOT office at 860 Jupiter Park Drive, Suite 2 in Jupiter.

Project officials will be on hand to answer questions. There is no formal presentation planned.

The meeting is free and open to the public.

Construction is expected to start on May 9.

Lane closures will occur Sunday through Thursday nights from 9 p.m. until 6 a.m.

At least one lane in each direction of I-95 will remain open while the night work is being done, according to the Florida Department of Transportation.

For information, go to d4fdot.com.

road work

Signs to give motorists advance notice of any ramp closings on Indiantown and Bridge roads will be posted two weeks prior to work being started, according to FDOT.

The work is expected to be completed in the fall of 2018.

Total cost is about $17 million.

The exact area for the I-95 work is from the C-18 Canal just south of Indiantown Road in Jupiter to just north of Bridge Road in Martin County.

That’s about 10 miles.

All I-95 lanes and entry/exit ramps in both directions will be resurfaced. Minor shoulder and guardrail repairs are planned. The southbound bridge approach slab at approximate mile marker 89.5 is planned.

West Palm Beach-based Community Asphalt Corporation is the contractor.